The reorder point formula is: reorder point = average daily demand x lead time in days + safety stock. When stock on hand falls to that level, you place an order, so that new stock arrives before you run out. Work it out per item and per location, because demand and lead times differ between stores and suppliers.
The reorder point is the stock level that tells you it's time to order. Set it too low and you run out while waiting for delivery. Set it too high and you tie up money in stock you didn't need yet. The formula is simple; the work is in choosing honest inputs.
Running stock in more than one place?
NaviaLabs shows every location's stock on one screen and lists what needs action today.
The reorder point formula
Reorder point = average daily demand x lead time (days) + safety stock
Average daily demand: units sold per day at that location. Lead time: days from placing the order to having the stock on the shelf. Safety stock: extra units to absorb busier days and late deliveries.
The first part, demand times lead time, is the stock you expect to sell while you wait for the order. Safety stock is the cushion on top.
The three inputs of the reorder point formula
Average daily demand
Use recent sales at the location you're calculating for, usually the last four to eight weeks. Two adjustments matter:
- Leave out days the item was out of stock. They show zero sales, but customers still wanted it. Counting them lowers the average and the reorder point with it.
- Use the location's own sales, not the business average. A chain-wide figure is wrong for almost every individual store.
Lead time
Lead time is the whole wait, not just the supplier's quoted delivery time:
- time to notice and raise the order;
- time to get it approved;
- the supplier's delivery time;
- time to receive, check and put the stock on the shelf.
If approval usually takes two days and the supplier quotes five, your lead time is at least seven. For a store restocked from your own warehouse, the lead time is the transfer time instead.
Safety stock
Safety stock covers the gap between average and reality: days when sales are higher than usual, and deliveries that arrive late.
Three ways to set safety stock
1. A fixed number of days
The simplest method: hold a few extra days of average sales.
Safety stock = average daily demand x safety days
Good for getting started and for items with steady sales. Choose more days for items where running out is expensive.
2. The maximum-and-average method
Uses your own worst recent cases.
Safety stock = (maximum daily sales x maximum lead time) - (average daily sales x average lead time)
This protects well but can be generous, because it assumes the busiest days and the slowest delivery happen together.
3. The statistical method
Uses how much daily sales vary.
Safety stock = Z x standard deviation of daily demand x square root of lead time (days)
Z sets how often you accept running out during a lead time: about 1.65 for 95% of cycles, about 2.33 for 99%.
This version assumes the lead time is steady. If deliveries vary a lot, the maximum-and-average method is safer.
The reorder point formula across several locations
Each location has its own demand and its own way of being restocked, so each needs its own reorder point.
| Location | Daily sales | Restocked by | Lead time | Safety stock | Reorder point |
|---|---|---|---|---|---|
| Main Warehouse | 30 | Supplier | 10 days | 90 | 390 |
| Store 1 | 12 | Transfer from warehouse | 2 days | 12 | 36 |
| Store 2 | 4 | Transfer from warehouse | 2 days | 4 | 12 |
The warehouse reorders from the supplier; the stores reorder from the warehouse. A store reaching its reorder point should trigger a transfer, not a purchase order, as long as the warehouse can spare the stock.
Reorder point vs reorder quantity
The reorder point tells you when to order. The reorder quantity tells you how much. A common approach is to order enough to cover a period of expected sales plus safety stock, minus what's on hand, then round up to the supplier's minimum order quantity and pack size.
Mistakes with the reorder point formula
- Using the supplier's quoted lead time only, ignoring approval and receiving time.
- One reorder point for every location.
- Never updating it. Recalculate when sales or suppliers change, and at least every few months.
- Counting stockout days as zero demand.
- Treating the reorder point as the order size. It's the trigger, not the quantity.
How the reorder point works in NaviaLabs
In NaviaLabs the reorder point is the minimum stock level for an item at a location. You can set it per store, give the product a default for every location, or keep an existing reorder level from your import. When stock is at or below it, the item appears as Critical on the Needs Attention list for that location.
When you reorder, NaviaLabs suggests a quantity that covers expected demand for the longer of 30 days or three lead times, plus safety stock, minus what's on hand, rounded up to the item's minimum order quantity and order multiple. A person approves it. See reorder suggestions.
Frequently asked questions
What is the reorder point formula?
Reorder point = average daily demand x lead time in days + safety stock. When stock falls to that level, it is time to place an order.
How do I calculate safety stock?
Three common ways: a fixed number of days of average sales; the maximum-and-average method (maximum daily sales x maximum lead time minus average daily sales x average lead time); or the statistical method (Z x standard deviation of daily demand x square root of lead time).
Is the reorder point the same as the minimum stock level?
Often, yes. Both mean the level at which you act. In NaviaLabs the minimum per item and location plays the role of the reorder point.
Should each store have its own reorder point?
Yes. Each location sells at its own rate and has its own lead time, whether from a supplier or a transfer from your warehouse, so each needs its own reorder point.
How often should I recalculate reorder points?
Whenever sales or lead times change noticeably, and at least every few months. Items that keep running out are the first to review.